<p>One of the major challenges in the overall construction process for the completion of the S.R. 36 project was managing traffic in a way that would minimize impact and maintain access to all the businesses and residential areas along the corridor,small and mini mobile drum asphalt mixing plant while still trying to maintain the job schedule.</p>
<p>“Being built under traffic, we did not have what I would call high-production rate days on this job because it was sort of piecemealed for the traffic control,” Busler said. “But we would come in of course and start with our base; once we got our bases in place, we would come in with our base layer of AS mix,road chip manufacturers in america and then follow that up probably the next day with the A mix, and then a couple days later come back with our BM mix so we could get traffic shifted.”Busler added that TDOT ran the modified mix through the bulk of the project. Once the entire template was constructed for the entire project length, the team came in to put the final surface mix on at once.</p>
<p>Crews had to build the two outside lanes first in each direction, while keeping traffic moving through the middle of the corridor. At certain stages, traffic would get shifted back to the outside lanes, one lane in each direction, while all the work was put in the middle between traffic.Vibratory Roller Prices
</p>
<p>“At one point, when we put traffic in the outside lanes, because of the grade differences, we had to put a barrier wall up, and then at multiple points we had to have crossovers to get to the other side because in some places we had anywhere between 5-10 ft of grade change,” Fuller said. “It was a real challenge keeping service to the businesses, homeowners and residents on the road without any major accidents and any major injuries to our workers and the traveling public.”</p>
<p>Fuller added that at one point in the construction process,Samoa sale inexpensive asphalt pavement sealants interstate traffic had to be diverted onto the project route, causing crews to shut down construction work in order to keep traffic moving through the area. “All the coordination between all our crews was great,” Fuller said. “They helped each other out. I’m very proud of the outcome.”</p>